Damaturu ultra-modern market to be completed in three weeks – Project manager

1
80681

Story from Sa’adatu MAINA, Damaturu

The contractor handling the construction of the Damaturu ultra-modern market has promised to complete and handed over the project to the Yobe government in the next three weeks.

Mr Bala Adamu Goni, Project Engineer of Euro Afric Energy, the company handling the project confirmed this in an interview with Neptune Prime correspondent in Damaturu on Friday.

It would be recalled that the contract for the project was awarded at N2.8 billion in October 2019, with a completion period of 12 months.

The project includes; construction of over 800 shops, abattoir, administrative building, fencing, exit gates and gatehouses, conveniences and vehicles’ parking space.

Others are concrete pavements, mosques, roads and drainages, electrification equipment, water supply, fire service and police outposts.

Goni said the project had already reached 85 per cent completion level.

“The original handing over date was in December 2020; that did not happen due to certain challenges.

“But I give you my word; this project will be handed over by end of July or latest by the first week of August.

“We have completed the shops and other important structures. What remains is laying asphalt and building the concrete pavement you are seeing.

“Right now we are applying Plaster of Paris and next week, by God’s grace, we will lay tiles,” he said.

The engineer commended the state government for its maximum support and cooperation in executing the project.

Neptune Prime reports that the state is currently constructing similar markets in Potiskum, Gashua and Nguru towns.

Follow the Neptune Prime channel on WhatsApp: https://whatsapp.com/channel/0029Va74ZvU2v1IqKByXoX3d

Do you have breaking news, interview request, opinion, suggestion, or want your event covered? Email us at neptuneprime2233@gmail.com

LEAVE A REPLY

Please enter your comment!
Please enter your name here