Defective, inadequate materials caused Plateau school building collapse – Official

The panel of investigations constituted by the Federal Government has unravelled the cause of the unfortunate collapse of a two-storey building of Saint Academy School in Jos, Plateau State.

The panel concluded that the building collapsed on the innocent students writing exam because of the use of substandard and weak materials.

Neptune Prime reports that a two-storey building housing Saint Academy, located at the Busa Buji community in the Jos North Local Government Area of the state, collapsed on Friday at about 8:30 am, killing 22 persons and trapping about 154 others who were later evacuated to various hospitals.

The Director General of the Nigerian Building and Road Research Institute (NBRRI), Samson Duna, at a press briefing on Tuesday in Jos, said there were several defects on the building as identified by preliminary investigations from the team formed by the Federal Government.

Duna was ordered to constitute a panel to look into the remote and immediate cause of the building collapse and make recommendations in line with the mandate of the institute.

READ ALSO: FCTA commences investigation into Abuja 4-storey building collapse

Duna also identified the dangers inherent in building collapses, causes, consequences and prevention strategies using a multi-faceted framework.

The report also said the slab reinforcement anchorage provided for the structure was inadequate.

“The committee has commenced its investigation. Preliminary investigation revealed that the physical observation of the building looks so distressed.

“The quality of concrete is in doubt because there was no boundary between the concrete and the steel reinforcement.

“The slab reinforcement anchorage provided was inadequate. The sizes of the footing (foundation) provided were lesser than the required number (1200 mm X 1200mm).

“A comprehensive report on the investigation will be presented after the investigation,” he said.

Professor Duna enjoined the government and other professional bodies in the construction industry to insist on integrity tests on all distressed buildings, especially those around the collapsed building site.

A ten-man panel headed by Professor Frederick Job of the Building Department at the University of Jos has one month to investigate and conclude findings on the remote and immediate causes of the school building collapse.

Proofreading and editing by Gift Luckson and Hafsat Aleeyu Muye,Editor and Journalist at Neptune Prime.